PDCA, the Deming cycle, as a DevSecOps service design process

devops - 2026-11-02

Second entry in the DevSecOps for Linux, applied series. The first entry defines DevOps, DevSecOps, the DORA metrics and the feature-branch workflow. This one covers the loop that decides what to build and whether it worked: PDCA (Plan, Do, Check, Act), also drawn as the Deming wheel. Chapter 2 of Marco Antonio Carcano's DevSecOps and DevOps for Linux: The Foundations, "Solution Lifecycle", calls it "one of the most used solution design frameworks" and builds its service design process on it. Rémi Poillot's French introduction adds the picture of the wheel held by a wedge. This entry puts the two together and applies them to a sysadmin's work: a security check rolled out to a team's repositories, and a VM provisioning chain made faster.

Where it comes from

Walter Shewhart, a statistician at Bell Laboratories, described a cycle for quality control. W. Edwards Deming, who learned it from him, taught it to Japanese industry in the 1950s, and it spread from there as PDCA. Deming later preferred PDSA, with Study in place of Check. In The Deming Institute's words, Check looks at "the success or failure of a Plan", while Study compares the actual results with the results predicted at the start, in order to revise the theory behind the plan. That is why the examples below write down a prediction in Plan: it makes Check more than "did it work?".

The four steps

The book and the article describe the same four steps. The book's version is aimed at a technical service, and it adds two details that matter in practice: Do is done on a small scale, and a successful Act standardises the change and rolls it out more widely.

  1. Plan: identify the problem or the opportunity, set the objectives, work out the resources needed (people, equipment, information) and the steps to reach the result, with deadlines. The article recommends a SMART objective: Specific, Measurable, Achievable, Realistic and Time-bound, so that Check has a number and a date to compare against.
  2. Do: carry out the plan on a small scale, collect data on the outcome and document what was done.
  3. Check: analyse that data. Were the objectives met, and where do the actual results differ from the expected ones (in quantity, quality, cost or time)?
  4. Act: act on what Check found. If the plan worked, standardise it and apply it on a larger scale. If it didn't, revise the plan and go round again. Either way, keep what worked as well as fixing what didn't.

The article draws the wheel rolling up a slope with a wedge behind it: the experience gained in a cycle is what stops the wheel from rolling back down. It also insists on learning from successes as well as failures, because a success nobody analyses isn't repeated on purpose.

A wheel split into four quarters, Plan, Do, Check and Act, rests on a slope labelled continuous improvement. A curved arrow shows it rolling up the slope. Behind it, a wedge labelled experience stops it from rolling back down.
The wheel climbs the slope one cycle at a time, and the wedge of experience stops it from rolling back. Drawn for this site after Rémi Poillot's picture.

The book's service design steps

The book turns the cycle into concrete steps for designing a service (its Table 2-2). The book doesn't sort the steps into the four phases; the Phase column below is this entry's reading. The last column is how each step looks with the tools this series uses.

Step What the book asks for Phase In our work
Gathering requirements Work with the product owner (the person on the business side who owns the request) to turn business requirements into technical ones, and fix the scope early Plan An issue that states the need, the scope and what is out of it
Challenging the requirements A request can hide a misconception; refine it to avoid building what isn't needed Plan Asking what the requested VM, port or access is for, before granting it
Find the right products Unless asked to build a product, look for existing ones that fit, and combine them if needed Plan Stock tools first: GitLab CE, Artifactory, upstream Ansible roles and collections
Initial design A first design from the products' documentation, without trusting it blindly; plan for maintainability and security from the start Plan An ADR (architecture decision record) for each choice, a threat model, naming conventions
Set up a lab environment Disposable instances for research and destructive tests, such as a risky upgrade; kept for the whole life of the service Do The Proxmox and RKE2 lab, containers, where roles, playbooks and Helm charts run first
Live demo Show the stakeholders a working subset of the features; it can send work back to the lab Do, Check A merge request reviewed with the requester, on a lab or review environment
Draw up the WBS document After the demo is approved, a work breakdown structure (WBS): the list of steps to get the project to production Act The issue split into tasks, one merge request each
Guess an estimate Effort, elapsed time and costs, once the WBS exists Act Effort and lead time per task
Go or no-go A business and financial decision: whether to continue, implement only part, and in which order Act The decision recorded in the ADR or the issue

The Initial design step asks for most of the security work. The book treats every service as an asset in the value chain: it must go through a risk assessment (what can go wrong and how badly) and a risk treatment (what is done about each risk) before it goes live. Planning for these in the initial design avoids rework later, rework that can even harm the service's maintainability. The design must follow the organisation's Solution Design Document, with any exception tracked and accepted by the enterprise architect and the security team. It must also state requirements for data integrity, confidentiality, availability and capacity, and give the components short, unique names that say what they are.

Two remarks close the book's section:

The same loop in a merge request workflow

Most of what a cycle needs already exists in a Git workflow. A merge request (MR) is GitLab's name for a pull request: a proposed change on a branch, reviewed and tested by the pipeline before it is merged into main. PDCA adds the order, and the habit of measuring before and after.

Step Question Where it lives
Plan What's wrong, how do we know, and what result do we expect, and by when? An issue with the problem, the current measurement (the baseline), a SMART objective and the predicted result; an ADR when the plan chooses between options
Do Try it, small and reversibly A feature branch and an MR, a pilot on one repository or one environment, a new check that doesn't block yet
Check Did the numbers move as predicted? Pipeline results, scanner reports, the DORA metrics, monitoring, the time people spent
Act Keep, adjust or drop? Merge and roll out (a shared CI template, an Ansible role, a runbook), or revert; record the lesson in the issue, the ADR or a postmortem

The article's wedge is experience: a lesson learnt is what keeps a person from rolling back. In a team, the same lesson has to leave people's heads to hold, because people go on leave, change jobs or forget. A blocking check, a role or a template carries it for everyone, including whoever joins next. In practice that means a pipeline job that fails when a secret is committed, a role every server gets, a template every new repository starts from, or a runbook linked from the alert. This is what the book means by "standardise": experience written down in a form that enforces itself.

A cycle on secret detection

Secret detection scans a repository for passwords, tokens and private keys committed by mistake. gitleaks is one such scanner: it looks for known patterns in files and in Git history.

A cycle on VM provisioning lead time

The Kickstart, cloud-init and Image Builder entry explains the three layers of a VM template. Lead time here is the time from a VM request to a VM that is ready for whoever asked for it. It is the provisioning counterpart of DORA's lead time for changes.

PDCA and the DevOps loop

The DevOps loop in the terminology entry (plan, code, build, test, release, deploy, operate, monitor) is the path of one change. PDCA is a loop on the service and the way of working: it decides which changes to make to the service, the pipeline, the templates and the checks, then checks whether they paid off. The DORA metrics belong in Check, because they show whether a cycle made delivery faster or safer, not just busier. A blameless postmortem after an incident is a Check and an Act on a failure nobody planned.

Where the cycle usually breaks

In short